Shiradi Ghat reconstruction may not start immediately
Tuesday, January 3rd, 2017Mangaluru: The reason behind the repeated postponement of the second phase of reconstruction work on Shiradi Ghat road has now been revealed the contractor has not gathered 70 per cent of the material required for the work nor has he completed the extension of 74 culverts on the stretch. As a result, it is highly […]